   The project consists of Phase II of the access road rehabilitation.

    Following are approximate items and quantities for the base bid:

    BASE BID

Section 203

40

CY

Class 1 Excavation

Section 309

236

SY

SuperPave Asphalt Mixture Design, HMA Base Course, PG 64-22, < 0.3 million ESALs, 19.0 mm Mix, 4˝” Depth

Section 409A

3,510

SY

SuperPave Asphalt Mixture Design, HMA Wearing Course, PG 64-22, < 0.3 million ESALs, 9.5 mm Mix, 1˝” depth, SRL-L

Section 409B

5

TON

SuperPave Ashphalt Mixture Design, HMA Wearing Course (Leveling), PG 64-22, SRL-L

Section 491

2,668

SY

Bituminous Pavement Milling, 1˝” depth

Section 492

842

SY

Profile Milling

Section 606

1

EA

Inlet Grade Adjustment

Section 804

1

AC

Seeding and soil supplements, Formula B, including straw mulch w/ plastic mulch control netting

Section 808

Lumpsum

LS

Transplanting

Section 901

Lumpsum

LS

Maintenance and protection of traffic during construction

Section
962

911

LF

6” Yellow centerline marking

S-100

Lumpsum

LS

Contractor’s Plant

  

 

 

 

 

 

 

Last Updated 07/27/10

 
 